Water systems need TLC

$4 million in upgrades proposed
Durango’s wastewater-treatment plant sits near downtown, residential neighborhoods, next to the Whitewater Park, and Santa Rita Park, and a highway that carries thousands of tourists past it each year.

The city’s pumps, pipes, valves and other pieces of water infrastructure need $4 million worth of upgrades.

While it is not likely all the projects will make the city’s 2016 budget, Utilities Director Steve Salka on Tuesday made a strong case for many of the maintenance projects to the Durango City Council.

The intakes on both the Florida and the Animas rivers, a foundation piece of the system need to be upgraded. Some of the intakes on the Florida are almost 100 years old.

On the Animas River the city needs to install improvements to ensure enough water flows to the intake.

This intake is located near the Durango Whitewater Park, and the park has exacerbated a problem with the way the water flows through the channel. Right now, not enough water is flowing over the intake, Salka said.

The construction fix for the problem is estimated to cost about $250,000, and the Durango Parks and Recreation Department may contribute $100,000 to the project, he said.

This will help make sure the department is ready to rely more heavily on the Animas River during maintenance on Lemon Reservoir, which stores Florida River water. Work will be ongoing at the reservoir from August of 2016 through 2017, he said.

This likely won’t be the only construction in the Animas next year because the Utilities Department is also planning to replace four of the pipelines that cross beneath the river. These pipes are about 50 years old.

Many of the other projects Salka has planned focus on stainability at water-treatment plant and in other parts of the system.

Some of these projects include better insulation and variable-frequency drive pumps to reduce their demand for electricity.

He would also like to install larger compressors that would help eliminate the need for them to turn on and off constantly; this would address noise complaints from the Hillcrest neighborhood.

Eventually, Salka plans to install a solar garden that would fund the entire plant. But before the solar panels can be installed the La Plata Electric Association must install new equipment, and this project is not currently slated to happen in 2016.

Several councilors expressed some frustration this project hasn’t moved faster.

“I would love to see it moved to 2016,” said Councilor Sweetie Marbury.

Making the fencing around the plant more deer friendly is another, somewhat ancillary, project Salka proposed.

Deer often jump over the fence around the city reservoir, but some can’t make it back over.

“Our operators have to get in there and pull them off the fence,” he said.

He would like to build dirt ramps to allow the deer to get back out, and he estimates that the project could take $50,000.

The department will continue replacing water meters again the year by installing 300 new ones.

City crews have replaced 600 meters over the last two years, and it’s had a positive effect on the system.

“My revenue starts going up; we get more water accountability,” Salka said.

In dealing with the sewage system, Salka proposed $1.8 million in upgrades that will needed no matter what decision is made on the wastewater-treatment plant.

Councilors are debating whether to move the plant or renovate it at its current location in Santa Rita Park.

They will spend the next several months on these budget decisions, and they asked for Salka to bring them a holistic picture of how all the needed improvements including decisions on the plant will impact rate increases and the overall budget.