Concrete to be poured at Santa Rita midnight Tuesday

A concrete pour, the first of three, will be conducted from midnight to 8 a.m. Aug. 29 at the Santa Rita wastewater treatment plant, 149 S. Camino del Rio, as part of ongoing construction.

Construction flood lights will be used to illuminate the construction area. About 552 cubic yards of concrete will be pumped into the aeration basin as part of the slab.

To view live video of the project site, visit www.durangogov.org/santaritawrf.

For more information, call Gregg Boysen, project manager, at 375-4819.